What a Feasibility Study Should Deliver

The study of one well is, in practice, a study of the whole reservoir. Here is the scope that makes it reviewable — and the questions that separate a reservoir study from a well report in disguise.

A feasibility study exists to replace screening heuristics with site-specific, quantified, uncertainty-bounded answers. If it does not change what the project would do, it is not a study. The twelve deliverables below are what we consider a complete, reviewable basis for a single injection well — issued as a scope of work, a proposal checklist, or an acceptance test for a third-party report.

Twelve deliverables

DeliverableContentDecision it supports
Area and play screeningRegional geology, pressure and thermal regime, existing wells, analogue fields, preliminary capacity and containment assessmentWhether to spend money in this area at all
Structural framework and fault analysisHorizon and fault maps, fault seal and juxtaposition analysis, spill point and closure definitionContainment and the plume migration envelope
Stratigraphic and petrophysical modelFlow-unit correlation, rock typing, log–core calibration, property distributions with stated cut-offsCapacity and heterogeneity
Seal (cap rock) descriptionThe twelve-attribute framework with quantified seal capacity — see the checklistMaximum supportable CO2 column and containment confidence
Geomechanical modelStress tensor, rock strength, pressure envelope for reservoir, seal and faults, induced-seismicity screeningMaximum injection pressure and rate; hazard assessment
Fluid and geochemical modelBrine chemistry, CO2 properties at reservoir conditions, reactivity and compatibility assessmentInjectivity evolution, wellbore materials, miscibility for EOR
Static model with uncertaintyMultiple realizations, sensitivity ranking, capacity distribution at P90 / P50 / P10Probability that the required capacity exists
Dynamic simulationPlume and pressure forecasts over project life, sensitivity to key parameters, interference analysisWell count, spacing, rate, timing and monitoring design
Well design basisCompletion design, materials, injection rate and pressure limits, conformance strategyThe single-well design, properly bounded
Area of review and legacy wellsPressure-front delineation, well database review, integrity risk ranking, corrective action planPermit application and long-term liability
Monitoring, measurement and verificationBaseline programme, surveillance frequency, detection thresholds, decision triggersCompliance and public assurance
Risk register and economicsRanked subsurface risks with detection and mitigation, cost of each, and project value under uncertaintyGo / no-go and investment staging

Eight ways a single-well-only study goes wrong

Each of these is a case where the single-well report was accurate and the conclusion drawn from it was not.

What the well study showedWhat the reservoir actually didConsequence
Excellent injectivity in a 10 m high-permeability streakThe streak was a thief zone; 80% of injected volume entered it and the rest of the interval was bypassedFar lower usable capacity than modelled; early breakthrough; wasted capital on completion design
Healthy injectivity index in a short testPermeability was pressure- and saturation-dependent, or fines and salt precipitated over monthsInjectivity decline; inability to meet contracted volumes; costly workovers
Clean pressure build-up with no boundary seenThe test was too short to reach a sealing fault 800 m awayRapid pressure rise in a small compartment; throughput limited; extra wells required
Good local fracture gradientFracture gradient varied by 30% across the field because of stress heterogeneityInjection was pressure-limited at some locations; permitting assumptions invalid
Competent seal directly above the perforationsThe same seal thinned, became sandy 2 km away, and was cut by a fault near the plume marginPlume migration outside the modelled area of review; regulatory non-compliance and remediation liability
One well is sufficient at the tested rateThe pressure front reached offset wells and legacy penetrations within three yearsInterference, area-of-review expansion, additional monitoring and corrective action costs
The interval is present and porousIt shaled out across the northern half of the leaseHalf the planned storage volume did not exist; project economics reset after drilling
Oil recovery responded to CO2 in the pilot patternThe pilot sat in an unusually well-connected, low-heterogeneity part of the fieldField-wide EOR underperformed; sweep efficiency far below pilot prediction

Screening thresholds, and their limits

Screening criteria are for deciding where to look, not for deciding what to build. Every value below has been contradicted by a successful project. They are listed so that readers can interpret screening studies critically — not as acceptance criteria.

PropertyCommon screening indicationWhy it is only a starting point
DepthSupercritical conditions, typically deeper than 800 m depending on geothermal gradientDensity benefit versus cost and fracture gradient; some projects operate shallower or much deeper
PorosityGreater than 10–15% for storage; lower can work in fractured or vuggy rockPorosity is not capacity unless the pore space is connected
Permeability (kh)Order of 10 mD or better for single-well rates in the 1 Mt/yr classRate is set by drawdown allowance and interval thickness as much as by permeability
Net-to-grossGreater than 30–50% in the target intervalThin but high-quality intervals can outperform thick poor ones
Seal thicknessTens of metres, continuousContinuity and entry pressure matter more than thickness alone
Seal entry pressureWell above the buoyancy of the maximum credible columnThe correct comparison is to buoyancy, not to an arbitrary pressure
Fracture gradient marginMaximum injection pressure below fracture pressure of the confining zone, with marginThe relevant stress state varies laterally and with depletion or inflation history
Fault proximityAvoid faults that could be reactivated or that penetrate the sealFault seal analysis can qualify otherwise unattractive settings
Area of reviewSufficient acreage and pore-space rights to cover the pressure frontThe pressure front is modelled, not observed; sensitivity matters
Legacy wellsNo unassessed penetrations within the area of reviewAssessed and remediated wells can be acceptable
Fluid compatibilityNo severe scaling, halite or asphaltene risk at modelled conditionsManaged by design in many projects
HeterogeneityModerate Dykstra–Parsons coefficient and no dominant thief zonesHeterogeneity can be managed with conformance control if it is known

Fifteen questions to ask of any proposal

Whether the study is commissioned from Carbon Strategists or from anyone else, these questions separate a reservoir study from a well report wearing a reservoir study's clothes.

  1. Does the study define the area of review, and does it model the pressure front as well as the plume?
  2. What is the 3D structural framework based on, and how were faults mapped and classified as sealing or conductive?
  3. How was the confining zone characterised, and what is the quantified seal capacity in terms of supportable CO2 column height?
  4. What are the net-pay cut-offs, and how were they justified for this reservoir rather than imported?
  5. How many rock types were identified, and how does each flow differently?
  6. What is the vertical-to-horizontal permeability ratio, and how sensitive is the forecast to it?
  7. Were natural fractures characterised, and is there a fracture model with orientation and connectivity?
  8. What is the pressure envelope, and what limits injection rate — injectivity or pressure?
  9. What is the well count, and how does it change with the P10 and P90 permeability cases?
  10. Has the geomechanical model been calibrated to measured stresses, and what is the induced-seismicity screening result?
  11. How were legacy wells identified, assessed and ranked?
  12. What is the capacity distribution at P90, P50 and P10, and what drives the spread?
  13. Which measurements would most reduce the uncertainty, and what is each worth relative to its cost?
  14. What monitoring would detect each of the top three risks, and how quickly?
  15. What would make this project fail, and what would it cost to find that out before drilling rather than after?

The commercial argument in one paragraph

Injection wells, CO2 compression and surface facilities are sized by the reservoir model. Getting the well count wrong by a factor of two is the single largest avoidable capital error in a storage project — and it is invisible in a well report. Regulators also require site characterisation and an area-of-review analysis that a single-well dataset cannot support, while insurers price containment risk from the quality of the subsurface study rather than from the completion record.

Related

The full argument is in One Well Is Not a Reservoir; the measurement methods behind each deliverable are in the method catalogue; the seal framework is in cap rock description.

Scoping a study?

We will map these deliverables onto your data, your timeline and your permit strategy.

Start a scope